This week was a week for painting. The following images were taken to review the quality of painting inside and outside the house. The front porch and eaves were painted.

Just as a side note... Metricon insert into their original contract several hundred dollars for digging up the concrete footpath. As the next two photos show, this was not needed. Therefore it was requested for the amount to be credited back to us, and this was agreed to by Metricon. Make sure you check this as you will not be given back the money if you do not ask.


The painter agreed to paint this area a different colour.

The back of the front door and area surrounding.

A closer view of the roof of the portico area.

The double vanity area in the main bedroom.

As for appliances, the following photos were taken to keep a record of the appliances that were installed.

The double shower head configuration in the main bedroom ensuite.

The tiolet installed in one of the bathrooms.

The dishwaher installed into the kitchen.

The kitchen sink.

The bath in the back bathroom undergoing stress testing.

The Bi-fold doors. (Worth around $8500 in early 2010!)

The kitchen pantry shelves.